Update: College Mobility project (February 2015)

Following on from the completion of the design stage, a public procurement tender was released to select a vendor to supply and build the new Wi-Fi network which will comprise about 2,000 high performance Wi-Fi access points and associated infrastructure. The successful vendor has been selected and the new build stage will commence subject to governance approval and contract.

What happens next …

The vendor will require a four week lead time, after which the central resilient core of the new network will be commissioned and installed.  

We will develop a build-out schedule for high priority areas, such as student residences without Wi-Fi, and the schedule will be made available to the relevant areas for approval.  

We will make all efforts possible to avoid disruption due to these works during the revision and examinations period.